2023 Yosemite Street Waterline Replacement Project

Please excuse our mess! Our apologies in advance for the annoyance of traffic impacts and water shut-offs! Thank You for your patience and cooperation while we replace the waterlines to improve your neighborhood!


Schedule Update: 11/22/2023


North Segment (Please refer to Project Information Section and Exhibit)

The contractor's work on this segment (North segment) of Yosemite Street is complete. All lanes are open to vehicular traffic. There may be punch list items that need to be addressed. As such, you may see crews working to address these items. There should be minimal disruption to vehicular traffic during this period.


Thank you for your patience during the construction phase of this segment of the project.



Customers
Affected
LocationSegment
(North or South)
Date Water Service Impacted


No
Yosemite Street between Dry Creek Road and County Line Road
NorthN/A
NoYosemite Street between Easter Avenue and Dry Creek RoadNorthN/A
NoYosemite Street and Dry Creek Road intersectionNorthN/A



South Segment (Please refer to Project Information Section and Exhibit)

The contractor continues to work in the area between Park Meadows  Drive and C-470 (Site 2 - South Segment). This portion of the project has been delayed and as such the duration of the project has been extended (Site 2 - South Segment ONLY). The contractor has permitted with South Suburban Parks and Recreation for the approved trail closure & detour route to support active construction access, bore and open-cut pipe work at the Willow Creek crossing and between Willow Creek and C-470. This closure (Please see Trail Closure 1 and Trail Closure 2 below) will remain in place until installation, testing, final connections and interim restoration are complete in this area. We anticipate this work will be completed between mid-December 2023 and early January 2024.


Median restoration and final striping and paving on Yosemite Street has been completed.


Again, we deeply apologize for any inconveniences caused.

Customers Affected

Location

Segment
(North or South)
Date Water Service Impacted

NoSite 1 - Area located between Maximus Drive and Park Meadows Drive (Just west of South Metro Fire Station 34).
South

N/A
NoSite 2 - Area located between Park Meadows Drive and C-470 (North of Site 1).
South

N/A

No

Site 3 - Yosemite Street between Heritage Hills Parkway and Brook Hills Drive.
South

N/A


Maps of Work Area and Affected Customers (South Segment)

Site 2 - South

Yosemite Waterline Replacement Project South Segment Extended


Trail Closure and Detour 1
T Lowell Willow Creek Detour Lone Tree, CO MHT 1 TDa

Trail Closure and Detour 2

T Lowell Willow Creek Detour Lone Tree, CO MHT 1 TDProject Summary

*** Update: Site 2 - South Segment extended. Expected completion is between mid-December 2023 and early January 2024.


Work on the Yosemite Street Waterline Replacement has begun and is expected to be completed by November 17th, 2023. The work is divided into two (2) segments; the north segment (County Line Road to Easter Road) and the south segment (Brook Hill Drive to Park Meadows Drive) and as such takes place within the City of Centennial, City of Lone Tree, Douglas County, and SEMSWA jurisdictions (please reference Yosemite Street Waterline Replacement Exhibit below).  

A significant portion of the work takes place in residential streets and right-of-way. The work generally consists of constructing, installing, connecting, and testing approximately 14,500 lineal feet of 20-inch waterline (open cut and pipe bursting), 3,500 lineal feet of open cut 12-inch waterline, lateral connections, isolation valves, fire hydrants, blow-off assemblies, air release valves, and pressure regulating valves.

Images from ongoing work at the Yosemite Street Waterline Replacement Project (South Segment)

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8

Project Information:

LocationAlong Yosemite Street within the jurisdiction of the Cities of Centennial and Lone Tree:
  1. North Segment – County Line Road to Easter Road
  2. South Segment – Brook Hill Drive to Park Meadows Drive
DescriptionReplacement of approximately 14,500 lineal feet of 20-inch waterline (open cut and pipe bursting), 3,500 lineal feet of open cut 12-inch waterline, lateral connections, isolation valves, fire hydrants, blow-off assemblies, air release valves, and pressure regulating valves.
EngineerBurns & McDonnell Engineering Company, Inc.
ContractorT. Lowell Construction,Inc.
Project Contact: Tim Lowell II
(303) 435-6192


Contact Us

  1. Engineering


    Email Engineering


    Southgate Water & Sanitation


    3722 East Orchard Road
    Centennial, CO 80121

    Phone: 303-779-0261
    Fax: 303-779-0220

    Emergency:
    303-779-0261

    (Water breaks and sewer backups)

    Hours


    (Except holidays)
    Monday - Friday
    8 a.m. - 4:30 p.m.

    Staff Directory

Yosemite Street Waterline Replacement Exhibit

Yosemite Waterline Replacement Project Exhibit

The typical events occurring during waterline replacement construction looks like:

  • Set-up traffic control for the safety of workers, drivers, and pedestrians 
  • Pipe bursting in some area (this may include vibrations from associated activities)
  • Dig a trench for a section of waterline to be replaced 
  • Install the new waterline 
  • Backfill the trench and compact the soil 
  • Test the new waterline – we test to make sure it does not leak and that it is clean 
  • Fully connect the new waterline to the existing system 
  • Transfer water services from homes/businesses from the bypass/old waterline to the new waterline 
  • Open the street to traffic before moving on to the next section of pipe replacement 
  • Restore disturbed areas to similar conditions as before construction


NEIGHBORHOOD IMPACTS DURING CONSTRUCTION

  • Noise  
    • Contractors communicating, operating equipment and vehicles, backup beepers, etc. all generate more noise than typical. The back-up beepers are usually the most noticeable noise – these are required for workers and residents safety 
  • Unplanned Service Outages (includes water, gas, electric, internet, and phone) 
    • The contractor takes great care not to damage existing utilities, but sometimes utilities owners do not locate their existing utility in the dig area effectively (including Southgate).  Hitting an existing utility with the excavator will typically result in a service outage.  Note that these outages may not be reported to residents directly.  Call Southgate’s office for updates on unplanned service outages   
  • Road and Sidewalk Closures 
    • Lane closures will be required daily with approved traffic plans by City of Centennial and the City of Lone Tree
    • Notifications regarding “No-Parking” zones will be posted prior to construction on your street 
    • Access to driveways may be temporarily impacted while the contractor installs pipe in front of the driveway 
    • Please mind the “No-Parking” zones – ignoring no parking zones could result in towed vehicles 
    • For your safety, avoid the active construction areas and do not walk through construction zones 
  • Increased Traffic 
    • From the contractor executing work, inspectors making site visits, and detoured drivers to avoid construction zones 
  • Construction Materials Stored in the Streets 
    • The contractor will have materials temporarily stored in the streets, such as dirt piles and pipe, in anticipation of using the materials for construction
    • Messiness 
      • The streets will get messy with construction – the contractor will keep the streets and sidewalks as tidy as possible as they move through the project area 
      • At the end of the project, the contractor will do one big final cleaning of all the streets and sidewalks
  • Paving 
    • At the end of the project, the contractor will re-pave the street in accordance with City of Centennial and the City of Lone Tree standards 


PROJECT QUESTIONS OR EMERGENCIES (WATER LEAK OR SEWER SPILL)

Call Southgate at (303) 779-0261 (select option 8 after hours to speak with a Field Operator)